  "requirements": [
    {
      "severity": "critical",
      "category": "TITLE / LEGAL",
      "title": "Five recorded interests are shown to be vacated",
      "text": "Two utility/drainage/maintenance easements, one pedestrian easement, one telecommunications easement and one public right-of-way are separately keyed by instrument number.",
      "region": "vacation-core"
    },
    {
      "severity": "cost",
      "category": "PRECONDITION",
      "title": "Vacation is not the same as completed release",
      "text": "Pricing and site work must not assume the colored areas are clear until recorded vacation status and effective dates are verified.",
      "region": "legend"
    },
    {
      "severity": "critical",
      "category": "SURVEY / RFI",
      "title": "No easement area is certified",
      "text": "The sheet shows widths and graphic limits, but no closed legal-area schedule is printed; SF/acre quantities remain open.",
      "region": "plan"
    }
  ],
  "issues": [
    {
      "id": "CIV-ADDR",
      "title": "Project address requires reconciliation",
      "text": "This civil set identifies 308 8th Street West. The architectural/MEP takeoff set identifies 716 3rd Avenue Drive West. The layouts appear to describe the same development, but the governing parcel/address has not been confirmed."
    },
    {
      "id": "C5-02",
      "title": "Vacation status requires title confirmation",
      "text": "The plan says the five instruments are “to be vacated.” Confirm recording, effective dates and final title commitment before relying on the release."
    },
    {
      "id": "C5-03",
      "title": "No legal area schedule",
      "text": "Colored regions and several widths are shown, but no closed-boundary area table is printed. No SF or acreage is inferred."
    },
    {
      "id": "C5-04",
      "title": "Instrument descriptions must match title documents",
      "text": "Verify each instrument number, beneficiary and encumbrance against the current title package."
    },
    {
      "id": "C5-05",
      "title": "Later site work depends on cleared rights",
      "text": "Do not release foundations, utilities or paving within affected strips until the vacation chain is complete."
    }
  ]
}