  "sheet": "C-2",
  "requirements": [
    {
      "severity": "critical",
      "category": "UTILITIES / RFI",
      "title": "Existing utility information must be independently verified",
      "text": "Locations, sizes and types are approximate; contractor must investigate conflicts, coordinate owners and use subsurface utility notification before excavation.",
      "region": "utilities"
    },
    {
      "severity": "cost",
      "category": "EARTHWORK",
      "title": "Compaction and testing are contractor scope",
      "text": "Work includes geotechnical testing, 12-inch maximum lifts, proof rolling and corrective earthwork where required.",
      "region": "grading"
    },
    {
      "severity": "critical",
      "category": "EROSION",
      "title": "Inspection and maintenance are continuous obligations",
      "text": "Controls must be maintained, repaired and documented; the inspection form requires at least weekly review and within 24 hours after a storm event of 0.50 inches or greater.",
      "region": "erosion"
    },
    {
      "severity": "cost",
      "category": "RESTORATION",
      "title": "Disturbed improvements must be restored",
      "text": "Roads, walks, pavement, landscaping, utilities and adjacent work damaged by construction are contractor responsibility.",
      "region": "general"
    },
    {
      "severity": "critical",
      "category": "TRENCH / SAFETY",
      "title": "Utility crossings have prescribed clearances",
      "text": "The trench notes require minimum vertical/horizontal separations and flowable-fill or concrete encasement where clearances cannot be met.",
      "region": "trench"
    }
  ],
  "issues": [
    {
      "id": "CIV-ADDR",
      "title": "Project address requires reconciliation",
      "text": "This civil set identifies 308 8th Street West. The architectural/MEP takeoff set identifies 716 3rd Avenue Drive West. The layouts appear to describe the same development, but the governing parcel/address has not been confirmed."
    },
    {
      "id": "C2-02",
      "title": "Notes define scope but not quantities",
      "text": "C-2 is NTS and contains requirements only. No installed material quantities, lengths, areas or volumes are inferred from generic notes."
    },
    {
      "id": "C2-03",
      "title": "Stormwater inspection form is blank",
      "text": "Project name, operator, permit number, inspection entries and certifications must be completed during construction."
    },
    {
      "id": "C2-04",
      "title": "Utility ownership and conflicts remain open",
      "text": "The sheet disclaims completeness of existing utilities and requires field verification and coordination before work."
    },
    {
      "id": "C2-05",
      "title": "Geotechnical acceptance chain is incomplete",
      "text": "The notes require proof rolling, compaction testing and soil-consultant review; the governing geotechnical report is not linked on C-2."
    }
  ]
}